Raeford Road Median (Fayetteville)

Raeford Road Median (Fayetteville)
The map above shows only the project's general location. (View detailed maps.)
Project Information Left Table
County:Cumberland
Status:Under Construction
STIP Number:U-4405
Project Information Right Table
Estimated Cost:$204 million
Start Date:Spring 2022
Completion Date:TBD
​​​​​​Project Overview

Construction is underway to improve safety along 6.3 miles of Raeford Road (U.S. 401) between Old Raeford Road and Robeson Street in Fayetteville​ by replacing the open center turn lane with a median.

The road’s reconstruction also will improve traffic flow and pedestrian access.

The project will be divided into three segments (locations are approximate):
  • Segment A: Old Raeford Road to Bunce Road 
  • Segment B: Bunce Road to Brighton Road
  • Segment C: Brighton Road to Robeson Street
 
Each segment will be awarded separately as construction contracts, beginning with Old Raeford Road to Bunce Road in a contract that is scheduled to be awarded in the fall of 2021. The other segments would be built later.

Project Funding

This project is listed as Project U-4405 in the​ N.C. Department of Transportation's State Transportation Improvement Program and is funded for almost $204 million.

*Estimated costs subject to change

Project Timeline

*Future dates subject to change

Contact

Jason Salisbury, P.E.

Division Construction Engineer
Division 6

P.O. Box 1150
Fayetteville, NC 28302

Last updated Feb. 14, 2025