N.C. 43 Connector Final Phase

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​Project Overview

Planning and development are underway to build the final phase of the N.C. 43 Connector in Craven County. Proposed work would join U.S. 17 Business (Dr. Martin Luther King Jr. Boulevard) and the existing portion of the connector south of U.S. 70/U.S. 17.

The proposed N.C. 43 Connector will be built as a four-lane divided highway with a grass median which will be designed for highway travel.​

Project Funding

This project is listed as Project R-4463A in the N.C. Department of Transportation's State Transportation Improvement Program and is funded for $48.7 million.

​Estimated Cost*
​Project development and design​$2,750,000
​Property acquisition
​$4,475,000
​Utility relocation ​
​$1,275,000
​Construction costs​$40,200,000
​Total cost ​$48,700,000

*Estimated costs subject to change

Project Timeline

​​Milestone
​Date*
​Utility relocation begins 
​Fall 2024
​Construction begins 
​Fall 2025​

​*Future dates subject to change 