skip to main
Close Menu

Raeford Road Median (Fayetteville)

​​​​​Project Overview

Construction is underway to improve safety along 6.3 miles of Raeford Road (U.S. 401 Business) between Old Raeford Road and Robeson Street in Fayetteville​ by replacing the open center turn lane with a median.

The road’s reconstruction also will improve traffic flow and pedestrian access.

The project will be divided into three segments:
  • Segment A: Old Raeford Road to Bunce Road 
  • Segment B: Bunce Road to Glensford Drive
  • Segment C: Glensford Drive to Robeson Street
 
Each segment will be awarded separately as construction contracts, beginning with Old Raeford Road to Bunce Road in a contract that is scheduled to be awarded in the fall of 2021. The other segments would be built later.

Project Funding

This project is listed as Project U-4405 in the​ N.C. Department of Transportation's State Transportation Improvement Program and is funded for $147.8 million.

​Estimated Cost*
​Project development and design​$6,000,000
​Property acquisition​$51,600,000
​Construction costs​$90,200,000
​Total cost ​$147,800,000

*Estimated costs subject to change

7/26/2024 1:52 PM