skip to main
Close Menu

Miller Boulevard Widening in Havelock

Project Overview

Planning and development are underway to widen Miller Boulevard and N.C. 101 (Fontana Boulevard) to four lanes with a raised median between Lake Road to Outer Banks Drive in Havelock, Craven County. 

The purpose of this project is to alleviate traffic congestion, add capacity for anticipated growth in traffic and improve safety throughout the corridor, which will become a more prominent gateway to downtown Havelock after the Havelock Bypass​ is completed.



Project Funding​

This project is listed as Project U-3431 in the N.C. Department of Transportation's State Transportation Improvement Program and is funded for $60 million.

​Estimated Cost*
​Utilities 
​$3,000,000
​Right of way
​$17,300,000
​Construction costs​$91,500,000
​Total cost ​$111,800,000

*Estimated costs subject to change

11/21/2024 4:03 PM