 |
 |
Screening Process
The screening process is applicable for TIP Projects that will have an environmental document prepared by the Project Development and Environmental Analysis Branch.
General
As stated in the MOU, the Section 404/NEPA Merger Process will generally
apply to all new location projects and all projects that will likely require an
individual permit under Section 404 of the Clean Water Act. Additional guidance
is provided to assist in identifying specific projects that will follow this process.
It is recognized that there are substantial benefits in carrying projects through the
Merger Process. the Merger Process requires a high degree of
commitment of resources by the many agencies that are involved in the process.
Consultation between the USACE, FHWA, NCDENR, and NCDOT to determine
applicability is necessary and important.
The guidance listed below will be used in determination of projects to be moved
through the Merger Process:
New Location and Widening Projects:
- Projects will be placed in the Merger Process if an Individual Section 404 permit is likely.
- If a Section 404 regional or nationwide permit is likely and the project potentially impacts:
- Critical Water Supply Area or
- Total Direct Impacts > one acre of wetlands or > 500 feet of stream
then:
FHWA, USACE, NCDENR and NCDOT will consult prior to scheduling the Concurrence Point No. 1 meeting to determine if the project should be placed in the Merger. Other resource agencies may be consulted for input as appropriate.
Bridge Projects
Question 1:
Is the project a replace in-place (in existing right-of-way) only bridge project?
ANSWER:
If the only alternative under consideration is replace in-place with off site detour, then no merger should be needed. If not proceed
Question 2:
Is an Individual Permit (IP) required from USACE?
ANSWER:
If an IP is required, or is likely to be required due to potential project impacts; then the NCDOT Rep. will consult with USACE, NCDENR, and FHWA to determine if merger is recommended.
Question 3:
Does the project involve potential impacts to or involvement with two or more of the following types of resources?
Wetlands
Buffer Rules
Water Supply Critical Areas
CAMA – Areas of Environmental Concern
T&E species present
Section 4(f)/Section 106
Environmental Justice
Unusually high level of public controversy
Unusually large number of relocations for project type
Compelling reason[s] to maintain traffic onsite
ANSWER:
If so, NCDOT will consult with USACE. NCDENR, and FHWA to determine if merger is recommended.
Guidance for Applicability Determination
The consultation between the FHWA, USACE, NCDOT, and NCDENR should
generally be a meeting so that all data can be reviewed including aerial
photography. Phone calls and e-mail may also be appropriate for certain level of
impacts that do not require a detailed review of data. In reviewing the potential
impacts of widening and new location projects, it is important to consider the
potential conflict of the important natural resources noted above with project
settings, intensity of impacts and important socio-economic (human) resources
such as Environmental Justice Communities, Section 4(f) properties, and
relocations. The need for detailed alternative analysis studies to avoid impacts to
these important resources and evaluate the conflict between resources should
determine the basis for applying the merger process to projects. The NCDOT
Project Development Engineer will document the results of this consultation and
provide copies to FHWA and USACE.
If the project team members for USACE, FHWA, NCDENR and NCDOT cannot
reach agreement, the decision will be referred to the USACE’s NCDOT
Coordinator, FHWA’s Operations Engineer, NCDENR Deputy Secretary or
designee, and NCDOT’s Manager of the Project Development and
Environmental Analysis Branch for resolution.
Non-Merger Projects
For projects that do not go through the merger process, it is important to note
that NCDOT will still be fulfilling the avoidance and minimization requirements.
Resource agencies will have the opportunity to review these projects through the
normal NEPA and permitting process when the EA is circulated for comments or
when the CE is signed. Additionally, for projects designated by the USACE,
FHWA, NCDENR and NCDOT, NCDOT will hold a meeting with appropriate
agencies to obtain their input on the adequacy of the avoidance and minimization
measures achieved, prior to circulating the EA for comments or when the CE is
signed.
If information becomes available on a non-merger project that warrants it being
considered for placement in the merger process, USACE, FHWA, NCDENR, and
NCDOT will meet to determine if it should be placed in the merger and at what
point based on the project status.
Projects in Merger
As the project development advances and more detailed information becomes
available, it may be possible to determine that a project in the merger does not
need to remain in the merger. At each concurrence meeting, the Project Team
should evaluate the need for the project to stay in the merger process. If these
agencies agree, the project may be dropped from the merger. The final decision
to remove a project from the merger process rests with NCDOT, NCDENR,
USACE, and FHWA. The project development engineer will document the results
of the consultation and provide copies to all project team members.
|
 |
 |