Sample Earthwork Input - Corridor Modeling


XSECTION

Earthwork

tolerance = 0.01

xs dgn = [TIP]_RDY_XSC_[DESC].DGN

Proposed Finish Grade
   soil type = suitable
   fill mult factor = 1.00
      type = line, line_string
      lvname = Prop CMT Slope Grass Earthwork
      lvname = Prop CMT Shld Grass
      lvname = Prop CMT Shld Paved Cors1 Top
      lvname = Prop CMT Pavmt Cors1 Top
      lvname = Prop CMT Subgrade Earthwork

Existing Ground Line
   soil type = suitable
      type = line, line_string
      lvname = Exist XS Ground Line

Write Earthwork Shapes
   plot param
      lvname = Prop XS Earthwork Shape
      Stratify Shape Color

End Area Decimal Places = 0

process earthwork for baseline = L
   job number = rdy
   beginning station = 11+30.00
   ending station = 12+75.73

process earthwork for baseline = L
   job number = rdy
   beginning station = 14+05.73
   ending station = 15+00.00

 


 

Detailed Diagram of Corridor Modeling Earthwork Elements Break Down

 

Disclaimer: The content on the CADD Tutorial Web Pages are to be use as a general guide in producing a set of NCDOT Roadway plans. It should not be used as the sole reference to seal a set of plans. All other official manuals, such as THE ROADWAY DESIGN MANUAL and AASHTO A POLICY ON GEOMETRIC DESIGN OF HIGHWAYS AND STREETS (The "Green" Book) take precedence. The content contained on the CADD Tutorial web pages has no legal merit.